Control joints, or contraction joints, are cracks planned to occur during the shrinkage process.
Shrinkage is caused by temperature and moisture changes and happens regardless of the addition of control joints. When the concrete inevitably shrinks and cracks, we want to control where the crack takes place rather than it cracking randomly across the slab. Hence the name control joint. The vast majority
of shrinkage occurs within the first year of placement, especially the first 90 days, but the slab will continue to shrink for years which will cause the joint to widen over time. Joint filling should be put off
for as long as possible to allow the joint time to expand.